Promoting Efficiency in the Hydropower Licensing Process
MCLI Recommendation: “Congress should reform the hydropower licensing and permitting program by statutorily designating FERC as the lead agency, for purposes of NEPA review, for all licenses and other authorizations required under federal law.”
LPDD Recommendation: “Congress should reform FERC’s license amendment process by implementing a fast-track procedure for efficiency upgrades, modernization activities, and upgrades that are not anticipated to produce significant environmental effects.”
LPDD Recommendation: “To address state-law requirements requiring the state to conduct any required environmental review in conjunction with state action authorized under federal law, Congress should provide for states to participate as a cooperating agency with FERC, while providing opportunity for states to complete additional reviews under state law that are beyond the scope of NEPA.”
LPDD Recommendation: “To help ensure that agencies have needed resources to fulfill their responsibilities under federal law, Congress should provide optional mechanisms for agencies to receive direct funding from hydropower license applicants.”
LPDD Recommendation: “To help promote timely participation by the hydropower applicant and participating resource agencies, Congress should empower FERC to establish a centralized schedule for the completion of all licenses and authorizations required for a nonfederal hydropower project. To ensure that all participants meet the deadlines set forth in the centralized schedule, Congress should include appropriate enforcement mechanisms.”
LPDD Recommendation: “To help reduce redundancy in environmental studies and ensure sufficient time to complete all needed studies, Congress should direct FERC and all other resource agencies to develop a single comprehensive study plan at the beginning of the federal approval process, which will inform agency decisionmaking under all licensing and permitting requirements under federal law.”
LPDD Recommendation: “To prevent ex parte communications between decisional staff within FERC and cooperating agencies, Congress should direct all cooperating agencies to promulgate regulations that separate cooperating and decisional staff in the hydropower process.”
Filter by
No resource type matches that.
No jurisdictional level matches that.
15 resources
Water Resources Reform and Development Act of 2014
The Water Resources Reform and Development Act of 2014 established budgetary penalties against the Army Corps of Engineers for failing to meet deadlines established in a centralized permitting schedul...
FERC report, Hydroelectric Licensing Policies, Procedures and Regulations
In 2001, FERC concluded a comprehensive investigation of the hydropower licensing process, titled Hydroelectric Licensing Policies, Procedures and Regulations: Comprehensive Review and Recommendations...
Proposed HR 8, the North American Energy Security and Infrastructure Act of 2015
Proposed HR 8, the North American Energy Security and Infrastructure Act of 2015, would have prescribed requirements for: (1) concurrent federal and state hydropower license application reviews, (2) i...
Oregon’s Existing Water Rights Expedited Process
Oregon’s H.B. 2785 encourages micro and small hydropower development by alleviating some of the costs associated with hydropower permitting. H.B. 2785 established an expedited water rights review proc...
Hydropower Regulatory Efficiency Act of 2013
The Hydropower Regulatory Efficiency Act of 2013 (Public Law 113-23) increases from 5,000 to 10,000 kilowatts the size of small hydroelectric power projects which FERC may exempt from its license requ...
Vermont’s Small Hydropower Assistance Program
Vermont’s Act 165 (S.148) directs the state to enter into a MOU with FERC to simplify the regulatory review process for small hydropower projects. After consulting with Colorado on their experience co...
2017’s Proposed S. 1460
2017’s proposed S. 1460 would have reformed the hydropower licensing and permitting program by statutorily designating FERC as the lead agency, for purposes of NEPA review, for all licenses and permit...
Proposed Community and Hydropower Improvement Act (S.1521, 2023)
In 2023, the Community and Hydropower Improvement Act (S.1521) was introduced in the U.S. Senate. This bill modifies requirements for hydropower projects, including by accelerating and coordinating th...
Energy Policy Act of 2005
The Energy Policy Act of 2005 outlined processes for natural gas pipeline certification. The legislation granted jurisdiction to the courts to take action where an agency fails to take timely action, ...
Proposed HR 2872 of 2017
Proposed HR 2872 of 2017, the Promoting Hydropower Development at Existing Nonpowered Dams Act, would have established an expedited licensing process for issuing and amending licenses and preliminary ...
FAST Act
The Fixing America’s Surface Transportation Act outlined regulatory process improvements to encourage timely agency decisions through the publication of agency status reports under the federal permitt...
Colorado’s Streamlined Federal Permitting Assistance Service for Small Hydropower
In 2010, Colorado and FERC entered into an MOU to encourage the development of small hydropower. The MOU required the state to prescreen proposed hydropower projects and submit the exemption applicati...
2017’s Proposed HR 3043
2017’s proposed HR 3043, the Hydropower Policy Modernization Act, would have designated FERC as the lead agency for coordinating all federal authorizations and reviews related to hydropower license ap...
Army Corps of Engineers and FERC MOU on reducing red tape
The Memorandum of Understanding Between United States Army Corps of Engineers and the Federal Energy Regulatory Commission on Non-Federal Hydropower Projects (2016) was adopted in order to spur change...
American Water Infrastructure Act
The American Water Infrastructure Act of 2018 created a fast-track procedure for the licensing of efficiency upgrades at hydropower facilities, as well as modernization activities and upgrades that ar...