California Order Streamlining Transmission Permitting

In January 2025, the California Public Utilities Commission adopted a decision to make it easier and faster to approve and build electric transmission projects and related grid upgrades in California. The Order includes early consultation requirements, establishes a “Rebuttable presumption” of transmission need, simplifies reporting requirements, and allows applicants to submit their own draft versions of environmental review documents.

Documents

  • Existing Laws

    GENERAL ORDER NO. 131-E

    Download
  • Existing Examples

    Information Sheet: CPUC Adopts Decision to Streamline Transmission Permitting

    Download